Central Distribution Project, Phase V

Project Stages

The development stages in the projects are displayed in the standard sequence for the industry. However, projects may be developed in a different sequence because of corporate decisions or events that push the owner to repeat stages. To access the full details of this project’s history please explore its milestones


Early Works
Early design & engineering
Start: 11/2013
In Construction
Operation
Current Stage In operation
Start:12/2015
Project Details

Description

The project aims for the need to adjust Mexico's power distribution infrastructure to the increasing production due the major domestic and industrial demand. Central distribution phase five includes the following infrastructure: five transmission lines with 115kV and 23kV stretching total 175km; 2.6km of high-tension underground lines; 3.7km medium-tension underground lines; 5.7km low-tension underground lines; five substations with 115kV and 23kV and 80MVA capacity; and 29 feeder lines.


Only BNamericas Subscribers Can Access This Information.
Subscribe to BNamericas to gain better insight into project development and contract opportunities in Latin America.
  • Early-stage and under-development projects throughout the region
  • Project coverage focused on biggest investments in each country and sector
  • Project milestones highlighting planned and unplanned developments
  • Sales contacts within operators and contracted companies
  • Access to experienced research staff
  • Risk analysis of cost increases, scheduling conflicts and regulatory environment
Already a subscriber? Please, login

Milestones Log and News

Locked content

Dear visitor, this table includes insights that is only available for subscribers

Related Companies

Name Sector Country Relation
Locked content
Project Owners
Locked content
Construction
Dear visitor, this table includes insights that is only available for subscribers

  • * Figures and dates are as per the latest publicly available information, as well as information gathered by BNamericas reporters and analysts and are subject to change.

  • * Changes to original budget estimates are shown as the total figure available and may include interest, working capital, inflation adjustments and other contingencies in addition to capital expenditure.

  • * Amounts and overall results are shown in US dollars unless otherwise stated.

  • * BNamericas does not guarantee the sequence, accuracy, adequacy, completeness or availability of any information and is not responsible for any errors or omissions or for the results obtained from the use of such information. There are no express or implied warranties. In no event shall BNamericas, its agents, directors, officers, employees, representatives, successors, and assigns be liable for any damages of any nature in connection with BNamericas content.


Key Specs

Full Name
Central Distribution Project, Phase V
Project Type
Transmission
Development Phase
In operation
Project Status
Active
Project Capacity
115  kV (kilovolts)  Transmission
Investment
US$ 60mn
Completion Date
2015
Location

The project includes  works in Mexico’s central zone, in the state of Jalisco.

* The map coordinates provided above represent the approximate latitude and longitude, and not the exact location, of the project in question.


Locked content
Owner / operator
Locked content
Engineering Manager
Locked content
General and Business Manager
Locked content
Head of Supplies
Locked content
Line Proyects Coordinator
Locked content
Director of Investment Projects Financed
Locked content
Project Development Manager
Dear visitor, this table includes insights that is only available for subscribers