Brazil's next transmission auction: what's on offer?

Bnamericas Published: Friday, November 23, 2018
Brazil's next transmission auction: what's on offer?

Scheduled for December 20, Brazil's next transmission lines auction is projected to result in 13.2bn reais (US$3.47bn) in investment.

The amount compares with 6bn forecast from the latest round, which awarded all lots and registered the highest discounts on maximum prices in two decades. Higher discounts represent more potential savings for final consumemaybe revenue is better rs, as the winning consortiums' revenue will be considered when calculating electric power bills.

Bidders accepting the lowest annual revenue from operations are awarded 30-year concession contracts to build, operate and maintain power lines and associated substations. BNamericas takes a look at the projects on offer, which include improved electricity supply in the north region and better integration of supply from wind generation in the south.

LOT 1

Project goal: Electric power supply to Santa Catarina state's north region and Vale do Itajaí. In addition, it will supply the cities of Joinville, Jaraguá do Sul, Indaiail and Itajaí, all in Santa Catarina.

Deadline to complete work: 60 months

Estimated investment: 2.79bn reais

Maximum price: 452mn reais

Direct jobs: 5,538

LOT 2

Project goal: Expansion of transmission flow for power supply from thermo generation in Rio de Janeiro and Espírito Santos states.

Deadline: 60 months

Estimated investment: 1.33bn reais

Maximum price: 221mn reais

Direct jobs: 2,662

LOT 3

Project goal: Expansion of transmission flow for power supply from thermo generation in Rio de Janeiro and Espírito Santos states.

Deadline: 60 months

Estimated investment: 754mn reais

Maximum price: 125mn reais

Direct jobs: 1,507

LOT 4

Project goal: Expansion of transmission flow for power supply from hydro and solar generation in Bahia and Tocantins states, in addition to supplying Dianópolis and Gurupi in Tocantins.

Deadline: 60 months

Estimated investment: 699mn reais

Maximum price: 116mn reais

Direct jobs: 1,398

LOT 5

Project goal: Power supply to the west region of Santa Catarina state, with the aim of eliminating voltage problems in the distribution network.

Deadline: 60 months

Estimated investment: 366mn reais

Maximum price: 61.6mn reais

Direct jobs: 732

LOT 6

Project goal: Power supply to the west region of Santa Catarina state, eliminating the risk of future electricity restrictions.

Deadline: 60 months

Estimated investment: 134mn reais

Maximum price: 22.6mn reais

Direct jobs: 298

LOT 7

Project goal: Transmission flow from hydro generation in Amapá state and power supply in the Almeirim region of Pará state.

Deadline: 60 months

Estimated investment: 278mn reais

Maximum price: 44.5mn reais

Direct jobs: 694

LOT 8

Project goal: Transmission line LT 230 kV Itararé II-Capão Bonito is a solution to supply electricity to the Capão Bonito region of São Paulo state.

Deadline: 60 months

Estimated investment: 89.4mn reais

Maximum price: 15.2mn reais

Direct jobs: 223

LOT 9

Project goal: Power supply to the metropolitan area around Manaus city, in Amazonas state.

Deadline: 60 months

Estimated investment: 161mn reais

Maximum price: 28.0mn reais

Direct jobs: 321

LOT 10

Project goal: Integration of wind power generation in Rio Grande do Sul state, especially in the Escudo Rio-Grandense region, to the south coast and the Lagoa dos Patos coast.

Deadline: 60 months

Estimated investment: 2.43bn reais

Maximum price: 381mn reais

Direct jobs: 6,080

LOT 11

Project goal: Integration of wind power generation in Rio Grande do Sul state, especially in the Planalto das Missões region.

Deadline: 60 months

Estimated investment: 349mn reais

Maximum price: 55.1mn reais

Direct jobs: 872

LOT 12

Project goal: Integration of wind power generation in Rio Grande do Sul state, especially in the Coxinha de Santana region.

Deadline: 60 months

Estimated investment: 610mn reais

Maximum price: 96.3mn reais

Direct jobs: 1,525

LOT 13

Project goal: Integration of wind power generation in Rio Grande do Sul state, especially in the Serra Gaúcha region; increase supply capacity and reliability in the metropolitan area around Porto Alegre city.

Deadline: 60 months

Estimated investment: 777mn reais

Maximum price: 122mn reais

Direct jobs: 1,942

LOT 14

Project goal: Integration of wind power generation in Rio Grande do Sul state; studies to supply the south of Santa Catarina state.

Deadline: 60 months

Estimated investment: 1.21bn reais

Maximum price: 202mn reais

Direct jobs: 2,429

LOT 15

Project goal: Integration of Humaitá city in Amazonas state to the national power grid; increase supply capacity to the region of Porto Velho city in Rondônia state, so thermopower units that currently provide electricity to the area can be shut down.

Deadline: 60 months

Estimated investment: 61mn reais

Maximum price: 10.4mn reais

Direct jobs: 152

LOT 16

Project goal: Supply power to Oriximiná, Óbidos, Juruti no Pará and Parintins near the Amazon river in Pará and Amazonas states.

Deadline: 60 months

Estimated investment: 1.13bn reais

Maximum price: 187mn reais

Direct jobs: 2,253

To continue reading, subscribe to BNamericas to get all the information in this article and access to related news items and reports.

Subscribe to BNamericas and gain access to thousands of project profiles, key contacts and news.

Other projects in: Electric Power (Brazil)

Get critical information about thousands of Electric Power projects in Latin America: what stages they're in, capex, related companies, contacts and more.

Other companies in: Electric Power (Brazil)

Get critical information about thousands of Electric Power companies in Latin America: their projects, contacts, shareholders, related news and more.

  • Company: Brennand Energia
  • Brazilian energy company Grupo Brennand has an installed hydroelectric capacity of 583MW and 230MW in wind energy. It as a majority stake in the firm Banda de Couro Energética S...
  • Company: Energia Consult
  • Energia Consult, a Brazilian subsidiary of the Grupo Energia providing power generation services, is specialized in services of engineering, consulting and management of power g...