Tailing dams El Torito expansion

Project Stages

The development stages in the projects are displayed in the standard sequence for the industry. However, projects may be developed in a different sequence because of corporate decisions or events that push the owner to repeat stages. To access the full details of this project’s history please explore its milestones


Early Works
Current Stage: Environmental evaluation
Start: 01/2018
Completion: 04/2019
In Construction
Under Construction
Start: 05/2019
Completion: 05/2025
Operation
In operation
Start:05/2025
Project Details

Description

The project is the second expansion project of the El Torito Tailings Dump (TRET) and seeks to increase capacity by 54M, going from 181Mt to 235Mt. These works will not affect the productive processes of the "El Soldado" operation; The current tailings impel and transport system will be maintained, which will take the waste from the pumping station of the concentrator plant to the cyclone station, which will be relocated in the tailings dam. The increase in TRET capacity does not affect the way in which the structure is operated.

Only BNamericas Subscribers Can Access This Information.
Subscribe to BNamericas to gain better insight into project development and contract opportunities in Latin America.
  • Early-stage and under-development projects throughout the region
  • Project coverage focused on biggest investments in each country and sector
  • Project milestones highlighting planned and unplanned developments
  • Sales contacts within operators and contracted companies
  • Access to experienced research staff
  • Risk analysis of cost increases, scheduling conflicts and regulatory environment
Already a subscriber? Please, login

Milestones Log and News

Locked content

Dear visitor, this table includes insights that is only available for subscribers

Principal Works

Locked content
Dear visitor, this table includes insights that is only available for subscribers

Related Companies

Name Sector Country Relation
Locked content
Project Owners
Locked content
Consulting
Locked content
Consulting
Locked content
Consulting
Locked content
Consulting
Locked content
Consulting
Locked content
Consulting
Dear visitor, this table includes insights that is only available for subscribers

  • * Figures and dates are as per the latest publicly available information, as well as information gathered by BNamericas reporters and analysts and are subject to change.

  • * Changes to original budget estimates are shown as the total figure available and may include interest, working capital, inflation adjustments and other contingencies in addition to capital expenditure.

  • * Amounts and overall results are shown in US dollars unless otherwise stated.

  • * BNamericas does not guarantee the sequence, accuracy, adequacy, completeness or availability of any information and is not responsible for any errors or omissions or for the results obtained from the use of such information. There are no express or implied warranties. In no event shall BNamericas, its agents, directors, officers, employees, representatives, successors, and assigns be liable for any damages of any nature in connection with BNamericas content.


Key Specs

Full Name
Tailing dams El Torito expansion
Project Type
Wastewater treatment plants
Development Phase
Environmental evaluation
Project Status
Active
Project Capacity
 Wastewater treatment plants
Investment
US$ 78mn
Completion Date
2025
Lifespan
7
Location

The project is located in the current El Torito tailings dam, in the Nogales district, 25 km northeast of the city of Quillota and 20 km southeast of La Ligua.


* The coordinates indicated on the map represent the approximate latitude and longitude and not the exact location of the project.


Locked content
Owner / operator
Locked content
Strategic Sourcing Manager
Locked content
Mine Manager El Soldado
Locked content
Chief Operating Officer El Soldado and Chagres
Locked content
Project Manager
Locked content
Project Procurement Manager
Dear visitor, this table includes insights that is only available for subscribers