Agua Prieta Wastewater Treatment Plant

Project Stages

The development stages in the projects are displayed in the standard sequence for the industry. However, projects may be developed in a different sequence because of corporate decisions or events that push the owner to repeat stages. To access the full details of this project’s history please explore its milestones


Early Works
In Construction
Operation
Current Stage In operation
Project Details

Description

The Agua Prieta wastewater treatment plant is expected to treat roughly 80% of the wastewater produced in state capital Guadalajara, benefitting 4.1mn people living in the city's metropolitan area. It will have the capacity to treat 8,500l/s of wastewater, making it Latin America's third largest plant behind Chile's La Farfana and Mexico's Atotonilco de Tula plant in Mexico's Hidalgo state. The plant will be built and operated by a consortium led by ICA subsidiary Conoisa, Atlatec, and Servicios de Agua Trident under a 20-year concession.

Only BNamericas Subscribers Can Access This Information.
Subscribe to BNamericas to gain better insight into project development and contract opportunities in Latin America.
  • Early-stage and under-development projects throughout the region
  • Project coverage focused on biggest investments in each country and sector
  • Project milestones highlighting planned and unplanned developments
  • Sales contacts within operators and contracted companies
  • Access to experienced research staff
  • Risk analysis of cost increases, scheduling conflicts and regulatory environment
Already a subscriber? Please, login

Milestones Log and News


Related Companies

Name Sector Country Relation
Locked content
Project Owners
Locked content
Project Owners
Locked content
Project Owners
Locked content
Construction
Locked content
Regulator
Dear visitor, this table includes insights that is only available for subscribers

  • * Figures and dates are as per the latest publicly available information, as well as information gathered by BNamericas reporters and analysts and are subject to change.

  • * Changes to original budget estimates are shown as the total figure available and may include interest, working capital, inflation adjustments and other contingencies in addition to capital expenditure.

  • * Amounts and overall results are shown in US dollars unless otherwise stated.

  • * BNamericas does not guarantee the sequence, accuracy, adequacy, completeness or availability of any information and is not responsible for any errors or omissions or for the results obtained from the use of such information. There are no express or implied warranties. In no event shall BNamericas, its agents, directors, officers, employees, representatives, successors, and assigns be liable for any damages of any nature in connection with BNamericas content.


Key Specs

Full Name
Agua Prieta Wastewater Treatment Plant
Project Type
Wastewater treatment plants
Development Phase
In operation
Project Status
Active
Project Capacity
9  m3/s (cubic meter per second)  Wastewater treatment plants
Investment
US$ 248mn
Completion Date
2014
Lifespan
20
Location

The Agua Prieta wastewater treatment plant will be located on the northern boundary of the Atemajac river basin, Zapopan municipality, in Mexico's Jalisco state.

 * The map coordinates represent the approximate latitude and longitude, and not the exact location of the project.


Locked content
Owner / operator
Locked content
Owner / operator
Locked content
Owner / operator
Locked content
Person in charge of project
Locked content
Water, Drainage and Sanitation Deputy General Director
Locked content
Manager, Studies and Projects
Dear visitor, this table includes insights that is only available for subscribers