Simplício Hydro Plant (Unit I)

Project Stages

The development stages in the projects are displayed in the standard sequence for the industry. However, projects may be developed in a different sequence because of corporate decisions or events that push the owner to repeat stages. To access the full details of this project’s history please explore its milestones


Early Works
Awaiting construction decision
Start: 11/2006
Completion: 02/2007
In Construction
Under Construction
Start: 03/2007
Completion: 08/2018
Operation
Current Stage In operation
Project Details

Description

The project calls for the construction of the first generating unit of a hydro plant located on the Paraíba do Sul river, between the municipalities of Sapucaia, Chiador and Além Paraíba, some 360km from Belo Horizonte in the Minas Gerais and Rio de Janeiro states, Brazil.

Only BNamericas Subscribers Can Access This Information.
Subscribe to BNamericas to gain better insight into project development and contract opportunities in Latin America.
  • Early-stage and under-development projects throughout the region
  • Project coverage focused on biggest investments in each country and sector
  • Project milestones highlighting planned and unplanned developments
  • Sales contacts within operators and contracted companies
  • Access to experienced research staff
  • Risk analysis of cost increases, scheduling conflicts and regulatory environment
Already a subscriber? Please, login

Milestones Log and News


Related Companies

Name Sector Country Relation
Locked content
Project Owners
Locked content
Construction, Supplier
Locked content
Consulting
Locked content
Construction
Locked content
Regulator
Locked content
Financing
Dear visitor, this table includes insights that is only available for subscribers

  • * Figures and dates are as per the latest publicly available information, as well as information gathered by BNamericas reporters and analysts and are subject to change.

  • * Changes to original budget estimates are shown as the total figure available and may include interest, working capital, inflation adjustments and other contingencies in addition to capital expenditure.

  • * Amounts and overall results are shown in US dollars unless otherwise stated.

  • * BNamericas does not guarantee the sequence, accuracy, adequacy, completeness or availability of any information and is not responsible for any errors or omissions or for the results obtained from the use of such information. There are no express or implied warranties. In no event shall BNamericas, its agents, directors, officers, employees, representatives, successors, and assigns be liable for any damages of any nature in connection with BNamericas content.


Key Specs

Full Name
Simplício Hydro Plant (Unit I)
Project Type
Hydro
Development Phase
In operation
Project Status
Active
Project Capacity
334  MW (megawatt)  Hydro
Completion Date
2018
Location

The project is located on the Paraíba do Sul river, between the municipalities of Sapucaia, Chiador and Além Paraíba, some 360km from Belo Horizonte.

* The map coordinates provided above represent the approximate latitude and longitude, and not the exact location, of the project in question.


Locked content
Owner / operator
Locked content
Superintendent of Technical Information Management
Locked content
Superintendent of Generation Concessions and Permits
Locked content
Engineering, Environment, Projects and Business Development Manager
Locked content
Operations and Maintenance Manager
Dear visitor, this table includes insights that is only available for subscribers