CFE speeds up transmission line construction

- Monday, April 7, 2003

Related Image

Mexico's state power company CFE has stepped up the pace of construction of five transmission lines to ensure the continuity of power supplies, the CFE said in a statement.

The CFE renegotiated agreements with companies building the lines to set new start dates without paying a higher price or incurring higher financial costs for the constructors, the CFE said.

The CFE said in March it wanted to bring forward completion dates as part of a series of measures designed to reduce possible disruptions to power supplies due to a lack of rainfall and lower natural gas production from state oil company Pemex.

Start your 15 day free trial now!

cta-arrow

Already a subscriber? Please, login

The five lines in question are all north-south interconnection lines:

The US$93mn, 342km first phase of the line associated with the Tuxpan II, III and IV thermoelectric projects, which will start in August instead of November 2003.

The US$12mn, 125km third phase of the Tuxpan II, III and IV line.

The US$45mn second phase of the line associated with the Altamira II, III and IV thermoelectric projects, which will start in November 2003 instead of February 2004.

The US$37mn, 291km third phase of the Altamira II, III and IV line, which will start in November this year instead of March 2004.

The US$242mn, 594km Saltillo-Cañada line, which will start in December 2003 instead of May 2004.

Meanwhile, CFE also said that construction has started on a 232km line associated with the Rio Bravo III thermoelectric project, and is scheduled to start operations in May 2004.