Concessions for nearly 700MW expire in the Dominican Republic

The Dominican Republic’s national energy commission (CNE) has issued resolutions declaring the expiration of six provisional power concessions for nearly a combined 700MW.
A provisional concession expires when the developer does not carry out studies within the granted term (usually 18 months), according to the CNE, which highlights the need “for the smooth running and development of the sector.”
One of the resolutions is for a 73MW plant proposed by Consorcio Energético Puna Cana-Macao (CEPM) that would run on natural gas and heavy or light fuel oil.
Three other concessions that have expired are for Cotoperi Solar FV’s Cotoperi I, II and III projects in La Romana province. Each park would boast 54.2MW.
And two resolutions are for EGE Haina’s 400MW Quisqueya III plant in San Pedro de Macoris province that would run on natural gas, fuel oil and/or diesel, and the 60MW phase two of the Girasol solar park in San Cristobal province.
EGE Haina told BNamericas that they will continue with both projects, explaining that the regulatory framework allows for the renewal of expired provisional concessions.
CNE has already issued EGE Haina a new provisional concession for Girasol that includes another 18 months to carry out studies in the lead up to the definitive concession.
EGE Haina recently began construction of the 90MW Esperanza solar park.
CEPM and Cotoperi did not immediately respond to a request for comment regarding their projects.
Subscribe to the most trusted business intelligence platform in Latin America. Let us show you our solutions for Suppliers, Contractors, Operators, Government, Legal, Financial and Insurance.
News in: Electric Power (Dominican Republic)

Spanish partners’ 50MW Dominican Republic solar park secures grid access
Meanwhile, the government looks to launch a renewable energy supply call at year-end.

Spotlight: IDB's financing plans for the Dominican Republic
Representatives of the development bank told BNamericas about approved and planned operations in the energy, water, and infrastructure sectors.
Subscribe to Latin America’s most trusted business intelligence platform.
Other projects in: Electric Power (Dominican Republic)
Get critical information about thousands of Electric Power projects in Latin America: what stages they're in, capex, related companies, contacts and more.
- Project: Payita solar plant
- Current stage:
- Updated:
1 year ago
- Project: Martí solar park
- Current stage:
- Updated:
1 year ago
- Project: Punta Catalina thermo plant
- Current stage:
- Updated:
1 year ago
- Project: Powership KPS-8 combined cycle power plant
- Current stage:
- Updated:
1 year ago
- Project: Itabo III thermoelectric plant
- Current stage:
- Updated:
2 years ago
- Project: Maranatha solar project
- Current stage:
- Updated:
2 years ago
- Project: Girasol solar park (Phase I)
- Current stage:
- Updated:
2 years ago
- Project: Santiago - Los Naranjos solar photovoltaic plant
- Current stage:
- Updated:
2 years ago
- Project: Sunfarming Food & Energy solar park
- Current stage:
- Updated:
2 years ago
- Project: El Guincho Solar photovoltaic park
- Current stage:
- Updated:
2 years ago
Other companies in: Electric Power (Dominican Republic)
Get critical information about thousands of Electric Power companies in Latin America: their projects, contacts, shareholders, related news and more.
- Company: Corporación Dominicana de Empresas Eléctricas Estatales  (CDEEE)
-
This is an archived company in the BNamericas database. If you need an update on this company and its operations, please Ask Us. ________________________________________________...
- Company: Mercedes Adames Ingeniería
- Company: Atuc Solar Dominicana SRL