Panama’s 4th power transmission line advances with contract award

Bnamericas Published: Monday, November 28, 2022
Panama’s 4th power transmission line advances with contract award

Panama’s state power transmission company Etesa has awarded a contract to carry out easement studies for the country’s planned fourth main transmission line.

The winner of the 360-day contract was Consorcio Conavsa & CWORK LT4/Compañía Nacional de Avalúos and Civil Work with a bid of US$3.5mn, procurement information shows.

The other bidder was Consorcio Asociación Cuarta Línea/Manhattan PM (Panamá) and Avalúos Inspecciones y Construcciones (Avinco).

The consultancy works entail conducting commercial appraisal of land along the route of the 330km, 500kV Chiriquí Grande-Panamá III link, which will cross five provinces. The 1,280MW line would initially operate at 230kV.

The government plans to offer the project as a PPP.

Also read Proposed regulatory tweaks for Panama’s 4th power transmission project draw criticism

Subscribe to the most trusted business intelligence platform in Latin America. Let us show you our solutions for Suppliers, Contractors, Operators, Government, Legal, Financial and Insurance.

Subscribe to Latin America’s most trusted business intelligence platform.

Other projects in: Electric Power (Panama)

Get critical information about thousands of Electric Power projects in Latin America: what stages they're in, capex, related companies, contacts and more.

Other companies in: Electric Power (Panama)

Get critical information about thousands of Electric Power companies in Latin America: their projects, contacts, shareholders, related news and more.

  • Company: LNG Group Panamá S.A.  (LNG Group Panamá)
  • LNG Group Panamá S.A. signed an EPC contract with Consorcio Duro Felguera-IHI, a JV between Spanish engineering, procurement and construction contractor Duro Felguera S.A. and J...