Paraguay: ANDE receives 11 bids for construction of 500 kV Yguazú-Valenzuela transmission line
This Ande release was published using machine translation.
In the framework of the Valenzuela 500 kV Substation Construction and Interconnection Project, the opening of the 11 bids submitted by companies interested in the construction of the 500 kV line was held on Friday, November 25 of the current year double ternary Yguazú –Valenzuela, through the International Public Tender IDB -JICA N° 1684/2
The construction of the future 500 kV double ternary transmission line, which should be completed within 26 months, will connect in a stretch of 205 km, to the Yguazú Substation, located in the department of Alto Paraná, in the process of completion, with the Valenzuela Substation, in the department of Cordillera, in execution through the LPI ANDE FONPLATA N° 1561/2
The planned investment for the Yguazú-Valenzuela LT 500 kV construction work is estimated at USD 133,286,000, and will be financed through loans co-financed by the Inter-American Development Bank (IDB) and the Japan International Cooperation Agency (JICA), ad referendum of its approval by law of the Nation.
The construction of the 500 kV double ternary line, contemplated in the ANDE Master Works Plan for the period 2021-2030, is considered strategic for strengthening the Paraguayan electricity sector, and will enable energy integration of the countries of the region.
The companies that submitted economic bids are as follows:
- CIE SA
- CONSORCIO YGUAZÚ (Surveying and Road Engineering SA- SE.MI. SA- José Cartellone Civil Constructions SA,)
- CIE- ELECNOR CONSORCY (CIE SA- Elecnor Do Brasil Ltda.)
- CONSORCIO RT (Technoedil SA Construction Company- Rovella Carranza SA)
- YGUAZÚ ENERGY CONSORCY (Teyma Abengoa SA – Benito Roggio and Sons SA- LT SA)
- CONSORCIO SC – LT 500 kV (South American Electrical, Mechanical and Public Works Company SA (SACEEM)- Concret Mix SA)
- TCC CONSORCIO (Cobra Facilities and Services SA- TOCSA SA- Cymi Do Brasil Projects and Services Ltda)
- RIEDER & CIA. SACI
- RIEDER- INCOMISA- LT 500 kV CONSORCIO (RIEDER & CIA SACI- CONSTRUCTION AND ESTABLISHMENT INDUSTRY – INCOMISA)
- TECHNOELECTRIC SA
CONSORCIO YGUAZÚ 500 (Electrics of Medellín Engineering and Services SAS (EDEMSA)- Eight A SA)
Subscribe to the most trusted business intelligence platform in Latin America. Let us show you our solutions for Suppliers, Contractors, Operators, Government, Legal, Financial and Insurance.
News in: Electric Power (Paraguay)

How to achieve deeper energy integration in Latin America
Latin America has existing as well as under-construction international power links but the region’s potential in this area far exceeds what has bee...

ANDE inaugurates the Villa Elisa Substation to reinforce the electrical system in the Central Department
ANDE inaugurates the Villa Elisa Substation to reinforce the electrical system in the Central Department
Subscribe to Latin America’s most trusted business intelligence platform.
Other projects in: Electric Power
Get critical information about thousands of Electric Power projects in Latin America: what stages they're in, capex, related companies, contacts and more.
- Project: Bayóvar wind farm
- Current stage:
- Updated:
4 days ago
- Project: Mórrope wind park
- Current stage:
- Updated:
4 days ago
- Project: Ventos de São Roque 18 wind farm
- Current stage:
- Updated:
4 days ago
- Project: Norte Substation and Norte-Tequendama and Norte-Sogamoso transmission lines (First Reinforcement of the Eastern Area Network, Sogamoso Project)
- Current stage:
- Updated:
4 days ago
- Project: Serra do Seridó VI wind farm (Serra do Seridó complex - phase I)
- Current stage:
- Updated:
3 days ago
- Project: El Tornillito hydro project
- Current stage:
- Updated:
1 week ago
- Project: Copey-Fundación transmission line
- Current stage:
- Updated:
1 week ago
- Project: Copey-Cuestecitas transmission line
- Current stage:
- Updated:
1 week ago
- Project: Tirana Oeste photovoltaic park
- Current stage:
- Updated:
1 week ago
- Project: Manuel Belgrano II thermoelectric plant (TMB II)
- Current stage:
- Updated:
1 week ago
Other companies in: Electric Power (Paraguay)
Get critical information about thousands of Electric Power companies in Latin America: their projects, contacts, shareholders, related news and more.
- Company: SGS PARAGUAY S.A.
- Company: Instituto Geográfico Nacional (IGN)
- Company: Consorcio Stantec - Iatasa - Tecma
- Company: Consorcio MWH - ADE - ELC
- Company: Consorcio Siemens-Rieder 500kV
-
The Siemens-Rieder consortium is formed by Rieder & Cia, a Paraguay-based integrated solutions provider for energy industry, and Siemens, the global electrical engineering and e...