Termoguajira Power Plant will be the first to move towards 100% decarbonized electricity generation
This Minenergy release was published using machine translation.
Within the framework of the exercise of Government with the people that is being carried out in the department of La Guajira, the Minister of Mines and Energy, Irene Vélez Torres, announced that the Termoguajira power plant , from the Gecelca company, located in the municipality of Dibulla, is the first thermoelectric plant to decide unanimously and move towards 100% decarbonized electricity generation.
This thermoelectric plant with a capacity of 290 megawatts (MW) uses coal as the main fuel for its operation and natural gas as secondary and support fuel for the start-up of the units.
"This is great news for the country, but especially for the department of La Guajira, since the just energy transition is beginning to materialize and this territory will be zero carbon," said Irene Vélez Torres, Minister of Mines and Energy, who added that " from the Ministry of Mines and Energy we will be accompanying with technical advice and supporting the search for alternatives to finance this investment”.
Termoguajira will transition to renewable energy through a scheme that will include solar panels and energy storage systems through batteries. In addition, to provide stability to the network, the installation of synchronous capacitors is contemplated, which will allow the network to be strengthened.
The best technical capacity balance strategy is being established to make the most of the connection point and establish the proportion of panels and batteries necessary for the transition.
On the other hand, Gecelca's board of directors decided that it will promote the deployment of solar energy in the region through both individual and associative photovoltaic generation schemes in its area of influence in the municipality of Dibulla, joining the "Solar Outburst" initiative. of the Ministry of Mines and Energy.
The transformation of Termoguajira is the reference project for the consolidation of our plan "From Coal to the Future: TEJ plan in coal-fired thermoelectric plants in Colombia" contemplated in the TEJ Roadmap, allowing progress in the decarbonization of the matrix electricity in our country. This fact, together with Gecelca's immersion in the "Solar Outburst" is a bet that shows that the Just Energy Transition in Colombia advances in the Government of Change!
The Plan, currently under construction, contemplates giving guidelines on labor and productive reconversion in the areas of influence of the thermoelectric plants, integrating new socio-territorial relationship models in the projects, financing strategies for the transition, among others, and it expects to start its discussion with the different ones of the sector in September and to be published for comments in November 2023.
Subscribe to the leading business intelligence platform in Latin America with different tools for Providers, Contractors, Operators, Government, Legal, Financial and Insurance industries.
News in: Electric Power (Colombia)
WDC Networks: Cloudy solar outlook, but bright ICT sales
The distributor's CEO, Vanderlei Rigatieri, told BNamericas about the plans and market outlook for 2024.
El Niño prompts rising gas demand in Colombia
The thermoelectric segment consumed 355BBTU/d in December, up from 242BBTU/d the previous month, amid a prolonged drought that has reduced output f...
Subscribe to Latin America’s most trusted business intelligence platform.
Other projects in: Electric Power (Colombia)
Get critical information about thousands of Electric Power projects in Latin America: what stages they're in, capex, related companies, contacts and more.
- Project: Norte Substation and Norte-Tequendama and Norte-Sogamoso transmission lines (First Reinforcement of the Eastern Area Network, Sogamoso Project)
- Current stage:
- Updated:
1 month ago
- Project: Termosinifaná
- Current stage:
- Updated:
1 month ago
- Project: San Bartolomé hydroelectric project
- Current stage:
- Updated:
1 month ago
- Project: Potreritos solar park
- Current stage:
- Updated:
1 month ago
- Project: Río Córdoba - Bonda Transmission Line (Termocol)
- Current stage:
- Updated:
1 month ago
- Project: Chivor II and Norte substations and associated transmission line
- Current stage:
- Updated:
1 month ago
- Project: La Loma - Sogamoso 500kV transmission line
- Current stage:
- Updated:
1 month ago
- Project: Run-of-the-river hydroelectric project on the Guayuriba - GUAY river
- Current stage:
- Updated:
1 month ago
- Project: Magdalena wind farm
- Current stage:
- Updated:
1 month ago
- Project: Culantral wind farm
- Current stage:
- Updated:
1 month ago
Other companies in: Electric Power (Colombia)
Get critical information about thousands of Electric Power companies in Latin America: their projects, contacts, shareholders, related news and more.
- Company: SOWITEC Energías Renovables de Colombia S.A.S.  (SoWiTec Colombia)
-
SOWITEC Energías Renovables de Colombia S.A.S. (SoWiTec Colombia), incorporated in 2013 in Bogotá, is the local branch of the German wind developer SoWiTec, which is focused on ...
- Company: Moffatt & Nichol Sucursal Colombia  (Moffatt & Nichol Colombia)
-
The description contained in this profile was taken directly from an official source and has not been edited or modified by BNamericas researchers, but may have been automatical...
- Company: Canadian Solar Energy Colombia S.A.S.  (Canadian Solar Energy Colombia)
-
The description included in this profile was taken directly from an AI source and has not been edited or modified by BNamericas researchers. However, it may have been automatica...
- Company: Elawan Energy Colombia S.A.S.  (Elawan Energy Colombia)
-
The description included in this profile was taken directly from an AI source and has not been edited or modified by BNamericas researchers. However, it may have been automatica...
- Company: Vatia S.A. E.S.P.  (Vatia)
-
Operating since 1998, Colombian firm Vatia is dedicated to the generation and commercialization of electric energy for the domestic market. Vatia is headquartered in Santiago de...
- Company: Mecánicos Asociados S.A.S - MASA STORK  (Mecánicos Asociados)
-
MASA and STORK, with more than 35 years of experience in the hydrocarbon, petrochemical, power, industrial and mining sectors worldwide are dedicated to manage the integrity of ...
- Company: Celsia S.A.  (Celsia)
-
Celsia is the energy arm of the conglomerate Grupo Argos. The company boasts an innovative portfolio focused on energy efficiency and a drive to contribute positively towards su...