Franke Project

Project Stages

The development stages in the projects are displayed in the standard sequence for the industry. However, projects may be developed in a different sequence because of corporate decisions or events that push the owner to repeat stages. To access the full details of this project’s history please explore its milestones


Early Works
In Construction
Operation
Current Stage In production
Project Details

Description

The Franke open pit operation uses crushing, agglomeration, leaching and SX-EW processes to produce copper cathodes that would be transported by rail to Puerto Barquito in Chañaral for shipping. The operation is anticipated to produce 30,000t/y copper cathodes -- and a total of 260,000t copper cathodes over 8-9 years. The project required 500 workers during peak construction phase and has generated 400 jobs during the ensuing operational phase. It is run by Vancouver-based Quadra FNX Mining.

Only BNamericas Subscribers Can Access This Information.
Subscribe to BNamericas to gain better insight into project development and contract opportunities in Latin America.
  • Early-stage and under-development projects throughout the region
  • Project coverage focused on biggest investments in each country and sector
  • Project milestones highlighting planned and unplanned developments
  • Sales contacts within operators and contracted companies
  • Access to experienced research staff
  • Risk analysis of cost increases, scheduling conflicts and regulatory environment
Already a subscriber? Please, login

Milestones Log and News


Principal Works

Locked content
Dear visitor, this table includes insights that is only available for subscribers

Related Companies

Name Sector Country Relation
Locked content
Project Owners
Dear visitor, this table includes insights that is only available for subscribers

  • * Figures and dates are as per the latest publicly available information, as well as information gathered by BNamericas reporters and analysts and are subject to change.

  • * Changes to original budget estimates are shown as the total figure available and may include interest, working capital, inflation adjustments and other contingencies in addition to capital expenditure.

  • * Amounts and overall results are shown in US dollars unless otherwise stated.

  • * BNamericas does not guarantee the sequence, accuracy, adequacy, completeness or availability of any information and is not responsible for any errors or omissions or for the results obtained from the use of such information. There are no express or implied warranties. In no event shall BNamericas, its agents, directors, officers, employees, representatives, successors, and assigns be liable for any damages of any nature in connection with BNamericas content.


Key Specs

Full Name
Franke Project
Project Type
Copper, Open pit mining
Development Phase
In production
Project Status
Active
Project Capacity
30,000  t/y (tons per year)  Copper
 Open pit mining
Investment
US$ 159mn
Completion Date
2009
Lifespan
15
Location

The Franke mine is located in the Altamira district, near the southern limit of Chile's region II, some 77km south of Taltal city, 64km north of Diego de Almagro, 52km northeast of El Salvador, and 5km east of the site of the former train station Altamira, at an altitude of some 1,730m.

* The map coordinates represent the approximate latitude and longitude, and not the exact location of the project.


Locked content
Owner / operator
Locked content
Administration and Logistics Manager
Locked content
Environmental and Risk Prevention Superintendent