Chile power grid study identifies problem areas

By
Monday, November 10, 2014

The operator of Chile's northern SING grid published a study on the system, with the aim of ensuring the grid's safe operation and preventing outages.

The operator, CDEC-SING, recommended the replacement of power switches and current transformers that are overburdened when the system suffers short circuits and failures.

Start your 15 day free trial now!

cta-arrow

Already a subscriber? Please, login

Power switches in need of replacement include four at the Crucero substation and one at the Mejillones substation, the report said.

The study's release coincided with an outage last Friday affecting some 95,000 families in Atacama region (III).

CDEC-SING has proposed US$258mn in expansion works, including projects to strengthen the grid's trunk line system and to improve the supply of electricity to northern cities Iquique and Pozo Almonte.

The recommended works are outlined in a proposal that addresses scenarios including increased regional integration with neighbors Argentina and Peru as well as increased demand from the Collahuasi mine, the world's largest copper operation.