Cerro Verde - 4B Leaching Pad Project

Project Stages

The development stages in the projects are displayed in the standard sequence for the industry. However, projects may be developed in a different sequence because of corporate decisions or events that push the owner to repeat stages. To access the full details of this project’s history please explore its milestones


Early Works
In Construction
Operation
Current Stage In production
Project Details

Description

Leaching will allow activities to continue in 2027. The pad is designed to receive a total of 212Mt ore: 168.9Mt secondary sulfide ore from Cerro Verde and 43.1Mt oxidized ore from Cerro Negro. Cerro Verde is an open-pit copper and molybdenum mining complex. The project comprises two phases and will require a total of 565 workers. The mine is run by US-based Freeport-McMoRan Copper & Gold.

Only BNamericas Subscribers Can Access This Information.
Subscribe to BNamericas to gain better insight into project development and contract opportunities in Latin America.
  • Early-stage and under-development projects throughout the region
  • Project coverage focused on biggest investments in each country and sector
  • Project milestones highlighting planned and unplanned developments
  • Sales contacts within operators and contracted companies
  • Access to experienced research staff
  • Risk analysis of cost increases, scheduling conflicts and regulatory environment
Already a subscriber? Please, login

Milestones Log and News


Principal Works

Locked content
Dear visitor, this table includes insights that is only available for subscribers

Related Companies

Name Sector Country Relation
Locked content
Project Owners
Locked content
Project Owners
Locked content
Project Owners
Locked content
Dear visitor, this table includes insights that is only available for subscribers

  • * Figures and dates are as per the latest publicly available information, as well as information gathered by BNamericas reporters and analysts and are subject to change.

  • * Changes to original budget estimates are shown as the total figure available and may include interest, working capital, inflation adjustments and other contingencies in addition to capital expenditure.

  • * Amounts and overall results are shown in US dollars unless otherwise stated.

  • * BNamericas does not guarantee the sequence, accuracy, adequacy, completeness or availability of any information and is not responsible for any errors or omissions or for the results obtained from the use of such information. There are no express or implied warranties. In no event shall BNamericas, its agents, directors, officers, employees, representatives, successors, and assigns be liable for any damages of any nature in connection with BNamericas content.


Key Specs

Full Name
Cerro Verde - 4B Leaching Pad Project
Project Type
Copper, Open pit mining
Development Phase
In production
Project Status
Active
Project Capacity
30,000,000  t/y (tons per year)  Copper
 Open pit mining
Investment
US$ 50mn
Completion Date
2010
Lifespan
30
Location

Cerro Verde is located 30km from Arequipa city, at an altitude of 2.700m, in Uchumayo and Yarabamba districts of Peru's Arequipa province.